After several months of intensive work by the GESAB team, the renovation has been completed successfully thanks to the excellent cooperation and support of all parties involved in the project.
It was essential that the functionality of the service not be affected during the execution of the work.
The work included the replacement of all existing raised access flooring, consoles and custom furniture, the air conditioning system, the lighting system, as well as the installation of sound-absorbing treatment on all vertical surfaces.
Of particular note is the creation of a new space to house the Crisis Room, located above the control technician's office, which guarantees optimal visibility of the entire operations area.